Brewery, Kelheim

Extension to a production and energy building

Formwork system

PAX column formwork


Contractor

Guggenberger GmbH, Mangolding


Construction details

Two buildings,

partly one- and two-storey constructions

Base area:

Enclosed space:

 

 

240 m² and 620 m²

3.850 m³ und 7.150 m³


Special features

18 concrete columns constructed with PAX II galvanised

Column height: 5 m to 15 m

Column cross-section: 30 cm x 30 cm

From a column height of 10 m, concreting was carried out in 2 phases.